                                      Covid-19 Production assessments

                                      7 replies [Last post]
                                      Dougal Watson
                                      User offline. Last seen 1 week 3 days ago. Offline
                                      Joined: 5 May 2020
                                      Posts: 4
                                      Groups: None
                                      Is there a quick process of applying a reduced productivity to remaining activities on a programme to assess the impact of Covid-19? This is as a result of a reduced permitted workforce on site e.g. 66% efficiency v planned. Can this be done in a new calendar for example? I have been manually calculating and adjusting bars but is there an easier way. Thanks.

                                      Replies

                                      Dougal Watson
                                      User offline. Last seen 1 week 3 days ago. Offline
                                      Joined: 5 May 2020
                                      Posts: 4
                                      Groups: None
                                      Thanks very much everyone for your assistance.
                                      Rafael Davila
                                      User offline. Last seen 12 hours 8 min ago. Offline
                                      Joined: 1 Mar 2004
                                      Posts: 4864

                                      Please click the following link to download presentation pdf.

                                      Link to Quantities_Workloads_and_Production_Rates.pdf/file

                                      Best Regard,

                                      Rafael Davila

                                      Mojahid Kilani
                                      User offline. Last seen 1 week 3 days ago. Offline
                                      Joined: 25 Jul 2018
                                      Posts: 7

                                      Hi Dougal, 

                                       

                                      There is a simple method you can use it if the program is robust along with resources and cost have uploaded.

                                       

                                      If your program has been built on P6 software, you can select the in progress activities and put the required dates on the suspended dates and resume dates, having this done to all the required activities; this will not only shows it on the bar chart but it will be reflected on the resources and cost numbers. 

                                       

                                      Hope this will help you

                                       

                                      Kind Regards, 

                                      Mojahid

                                       

                                       

                                       

                                       

                                       

                                       

                                       

                                       

                                       

                                      Ben Taunt
                                      User offline. Last seen 17 hours 24 min ago. Offline
                                      Joined: 16 Jan 2012
                                      Posts: 99
                                      Groups: None

                                      Hi Dougal,

                                      My colleague Richard Ormerod, founder of Powerproject, has developed a series of webinars on these topics.  You can watch back the first in the series here: https://www.elecosoft.com/webinars/

                                      Hope these help,

                                      Ben @ Powerproject

                                      Rafael Davila
                                      User offline. Last seen 12 hours 8 min ago. Offline
                                      Joined: 1 Mar 2004
                                      Posts: 4864

                                      I suggest modeling activities affected by covid-19 using different shifts/month each with their adjusted productivity and resource quantity.

                                      • You will get adjusted activity durations as per shifts/month production rates as activities are delayed.
                                      • Resource quantity and productivity assumptions will be transparent and easy to adjust. As activities start to open-up more resources can be added.
                                      • You will get true resource reports.

                                      Otherwise adjust manually activities duration a time consuming and error prone procedure.  As production type activities durations are increased according to productivities other activities will be further delayed into different months with different productivities.

                                      I see no shortcuts.

                                      Activity-Gantt-Covid-1-Covid

                                      click image above and zoom.

                                      You shall also be able to perform Monte Carlo that will adjust all iterations based on probabilistic values of productivity.  Covid brings much uncertainty.

                                      MCP01

                                      MCP02

                                      Good Luck
                                       

                                      Playing with the calendars we may get wrong reports on resource requiremenrs in our project.

                                      Alexandre Faulx-B...
                                      User offline. Last seen 50 min 10 sec ago. Offline
                                      Joined: 20 Jan 2003
                                      Posts: 1307

                                      Hi Dougal,

                                      you actually could assign a "Covid-19" calendar to the activities in the covid perimeter; with 6 working hours per day instead of 8 (by example) and the assignment set to Effort on Allocation, Powerproject will increase the activity duration by 25%