                                      Overall vs Duration on Table Definition Dialog Box

                                      2 replies [Last post]
                                      Anu hans
                                      User offline. Last seen 1 day 13 hours ago. Offline
                                      Joined: 13 Nov 2017
                                      Posts: 11
                                      Groups: None

                                      I have created a column for Planned Percent Complete(PPC). When I opened the Table Definition Dialogue Box under Measure of Progress I can choose on drop down following options;

                                      Duration

                                      Overall

                                      Cost

                                      I'd like to know the difference when reporting progress between duration vs Overall please?

                                      Replies

                                      Anu hans
                                      User offline. Last seen 1 day 13 hours ago. Offline
                                      Joined: 13 Nov 2017
                                      Posts: 11
                                      Groups: None

                                      Thanks lot for your explanation

                                      Alexandre Faulx-B...
                                      User offline. Last seen 10 hours 20 min ago. Offline
                                      Joined: 20 Jan 2003
                                      Posts: 1307

                                      Hello,

                                      Applying Overall Progress to the summary tasks in the project means that Powerproject will calculate the completion % of the summary from the individual completion % of its subordinate tasks

                                      you can refer to the following page to better understand:

                                      https://help.elecosoft.com/powerproject/english/15.0.01/Content/HTML_Top...

                                      Alexandre