                                      Converting .pp (Asta) files to .xer (Oracle Primavera) and importing to P6 - tips

                                      4 replies [Last post]
                                      Marion Close
                                      User offline. Last seen 17 weeks 6 days ago. Offline
                                      Joined: 11 Apr 2006
                                      Posts: 13

                                      HI

                                      Can anyone provide a list of tips when saving a .pp file as an .xer file and importing to P6.  I always get error message in Asta, and when i import to P6, it crashes and forces me to Exit with an error code.

                                       

                                      I found an independent list (see below) but wanted to see if anyone knew of more?  Our contractor is currently working in Asta and will be migrating to P6 but I need to run a quick analysis of the integrity of the schedule as it stands and want to be sure I'm importing everything I need. 

                                       

                                      Thanks

                                      Replies

                                      Ben Taunt
                                      User offline. Last seen 16 hours 11 min ago. Offline
                                      Joined: 16 Jan 2012
                                      Posts: 99
                                      Groups: None

                                      Of course (support.elecosoft.com) but more importantly, you can also just give us a call directly and ask!

                                      Zoltan Palffy
                                      User offline. Last seen 20 hours 48 min ago. Offline
                                      Joined: 13 Jul 2009
                                      Posts: 2688
                                      Groups: None

                                      doesnt Asta have a knowledge base like Oracle does where you can look up the error code to find out what is causing the problem ?

                                      Ben Taunt
                                      User offline. Last seen 16 hours 11 min ago. Offline
                                      Joined: 16 Jan 2012
                                      Posts: 99
                                      Groups: None

                                      Hi Mike,

                                      What verison of Powerproject are you on?  We changed lots of the import/export functions in v15 onwards.  Latest helpfile is here: https://help.elecosoft.com/powerproject/english/15.0.02/Content/HTML_Topics/Conceptual/Starting_work/Primavera/Xfer_Primavera.htm

                                      Thanks,

                                      Ben @ Powerproject

                                      Mike Milewski
                                      User offline. Last seen 2 days 10 hours ago. Offline
                                      Joined: 10 Mar 2020
                                      Posts: 4
                                      Groups: None

                                      Dang - I was hoping for an answer on this question - I am trying to do this today, provide an Asta .pp file that can be uploaded into P6.