                                      Purpose of Retired activities in Schedule

                                      3 replies [Last post]
                                      Nathan Siva
                                      User offline. Last seen 6 days 23 hours ago. Offline
                                      Joined: 28 Apr 2014
                                      Posts: 25
                                      Groups: None

                                      Hi Expats,

                                      In one of my UK clients schedule, they advised  to retire completed activites and non performing activites in the schedule. and my collegues recommended to change the duration of non performed activities duration to 1D in the schedule to avoid those activities in critical path.

                                      Can you please explain the purpose of retiring the activities in the schedule?

                                      Replies

                                      Zoltan Palffy
                                      User offline. Last seen 22 hours 21 min ago. Offline
                                      Joined: 13 Jul 2009
                                      Posts: 2688
                                      Groups: None

                                      Glad I could help 

                                      Nathan Siva
                                      User offline. Last seen 6 days 23 hours ago. Offline
                                      Joined: 28 Apr 2014
                                      Posts: 25
                                      Groups: None

                                      Thanks for the detailed explanation Zoltan. it  makes sense.

                                      Zoltan Palffy
                                      User offline. Last seen 22 hours 21 min ago. Offline
                                      Joined: 13 Jul 2009
                                      Posts: 2688
                                      Groups: None

                                      an actviity can be in one of 4 categories

                                      not started

                                      in progress 

                                      completed

                                      modified in progress using suspend and resume

                                      whne you say retire completed I do not know what you mean ? I also do not know what a non performed actviities are

                                      if you mean the activities are no longer in the scope then I would should show the same actual start and finish date equal to the date that you were told that this activity is not longer in the scope. 

                                      PUtting 1 day duration WILL make them critical making them complted will not

                                      I would also assign an activity code theses and make a comment in the notes tab. This way you can filter and gropu these if need be. 