                                      P6 Filter

                                      2 replies [Last post]
                                      Heather Hadley
                                      User offline. Last seen 2 weeks 6 days ago. Offline
                                      Joined: 29 Jan 2019
                                      Posts: 15
                                      Groups: None

                                      I'm hoping someone can help me.  I need to filter my P6 schedule for a 2 week look ahead HOWEVER the PM is looking to also see all milestones - not just the ones within that 2 week period.

                                       

                                      Can anyone help?

                                      Replies

                                      Heather Hadley
                                      User offline. Last seen 2 weeks 6 days ago. Offline
                                      Joined: 29 Jan 2019
                                      Posts: 15
                                      Groups: None

                                      Thanks!!

                                      Santosh Bhat
                                      User offline. Last seen 10 hours 1 min ago. Offline
                                      Joined: 15 Apr 2005
                                      Posts: 260

                                      Heather,

                                      Use the top row of a filter to change the statement from "all" to "any" and then you can have three rows like this

                                      Row 1) Finish is less than DD+2w (if you want two weeks from the data date, CD+2w if you want from the current date)

                                      OR

                                      Row 2) Activity Type = Start Milestone

                                      OR

                                      Row 3) Activity Type = Finish Milestone