                                      Global Change - Status Indicator for expiry date alerts

                                      3 replies [Last post]
                                      THEO MANIFAVAS
                                      User offline. Last seen 2 weeks 4 days ago. Offline
                                      Joined: 11 May 2020
                                      Posts: 3
                                      Groups: None

                                      hi

                                      wandering if someone can please help me with this

                                      i have created a User Defined Field (UDF) named Insurance Expiry which i have allocated this with a date field so i can track when a resources liabilty insurance expires. 

                                      i have also created a UDF called Insurance Indicator which i have assigned Indicators as the date type for this UDF

                                       

                                      i then created 3 global changes

                                      7401
                                      global_change.jpg

                                       

                                      which i want to work as follows

                                      INSURACE EXPIRED = red cross indicator when Insurance Expiry date is after the data date (DD)
                                      INSURANCE EXPIRY WARNING = yellow warning indicator when Insurance Expiry date is within 10 days after the DD
                                      INSURANCE OK = green tick indicator when Insurance Expiry date is 10 days plus after the DD

                                      So the idea is that we enter the Insurance Expiry date for each resource and then based on scheduled DD, the Insurance Indicator column will display the correct indicator based on the parameters as detailed above. 

                                      I can't get this to work however so not sure if i'm entering the info wrong in the global change? see below

                                      7402
                                      modify_global_change.jpg

                                      or is there something else i'm meant to be doing to get it to work?
                                       

                                      thanks in advance

                                       

                                      Replies

                                      Zoltan Palffy
                                      User offline. Last seen 22 hours 20 min ago. Offline
                                      Joined: 13 Jul 2009
                                      Posts: 2688
                                      Groups: None

                                      when you say i have created a User Defined Field (UDF) named Insurance Expiry which i have allocated this with a date field so i can track when a resources liabilty insurance expires. 

                                      did you use start or finish date ?

                                      THEO MANIFAVAS
                                      User offline. Last seen 2 weeks 4 days ago. Offline
                                      Joined: 11 May 2020
                                      Posts: 3
                                      Groups: None

                                      hi

                                      thanks for pointing that out

                                      yes i did realise the last Global Change had CD instead of DD
                                      I was just trying to see if this worked over DD as i could't get the global change to work at all in terms of displaying the indicators within the activities view (the global change processes once you click Apply Change in terms of providing the report however this doesn;t then filter through into the activities view in the column) i.e this section remains blank 

                                       

                                      7403
                                      capture23.jpg

                                       

                                      just wandering if i'm missing a step or doing something wrong in the filter which is stopping it from displaying correcty?>(noting that the DD i have using the above exammple is set to 17/5/20 so the INSURANCE EXPIRY WARNING INDICATOR should come on but it doens't for some reason)

                                      Zoltan Palffy
                                      User offline. Last seen 22 hours 20 min ago. Offline
                                      Joined: 13 Jul 2009
                                      Posts: 2688
                                      Groups: None

                                      the last one you have cd not DD in the value 