                                      Calendar Days do not match Calendar Hours?

                                      3 replies [Last post]
                                      Rodney Jones
                                      User offline. Last seen 1 day 5 hours ago. Offline
                                      Joined: 18 Jun 2012
                                      Posts: 17
                                      Groups: None

                                      Hi,

                                       

                                      I have a calendar running 10 hours per day, 5 days per week. It is assigned as the Activity default calendar. When I create a new activity with a duration of 3 days and then change my User Preference to show Duration in Hours, the hours are only 24 but I expected them to be 30.

                                       

                                      Why is this happenning? 3 days on a 10 hour per day calendar should be 30 hours but it appears to be referencing an 8 hour day.

                                       

                                      You help would be greatly appreciated.

                                       

                                      Rod

                                      Replies

                                      Rodney Jones
                                      User offline. Last seen 1 day 5 hours ago. Offline
                                      Joined: 18 Jun 2012
                                      Posts: 17
                                      Groups: None

                                      Brilliant, Yes, it was the Timeperiods.

                                       

                                      Thanks.

                                       

                                      Rod

                                      Zoltan Palffy
                                      User offline. Last seen 22 hours 18 min ago. Offline
                                      Joined: 13 Jul 2009
                                      Posts: 2688
                                      Groups: None

                                      you have not set the hours correctly or have not set the correct default calendar  

                                      David Kelly
                                      User offline. Last seen 2 weeks 2 days ago. Offline
                                      Joined: 19 Oct 2004
                                      Posts: 583
                                      Modify your calendar, and tick the "Time periods" button. These values control the multiplier/divider for hours and days