                                      Converting MSP TO P6 with Activity Relationship

                                      5 replies [Last post]
                                      Nathan Siva
                                      User offline. Last seen 6 days 23 hours ago. Offline
                                      Joined: 28 Apr 2014
                                      Posts: 25
                                      Groups: None

                                      Hi Expats,

                                       I'm trying to convert one of my project from MSP to P6 due to client demand, but afted converted the file, I can't to see atcitivty relationship.

                                      Is any way convert MSP to P6 with relationship and Activity Code

                                      Thanks,

                                      Replies

                                      Sterling Gallagher
                                      User offline. Last seen 9 hours 30 min ago. Offline
                                      Joined: 4 Oct 2019
                                      Posts: 12
                                      Groups: None

                                      Hi Nathan Siva

                                      Xertransfer will do what you are looking for.  You can download a 30 day trial and I am happy to give you a zoom orientation to give you a run throughof how it works.  Send an email to support@xertransfer.com after you download and I will assist you.  Please note you will need Microsoft Ppoject 2013 or later to use XerTransfer.

                                       

                                      https://xertransfer.com/trial/

                                       

                                      Regards

                                      Sterling

                                      Director XerTransfer

                                       

                                      Zoltan Palffy
                                      User offline. Last seen 22 hours 24 min ago. Offline
                                      Joined: 13 Jul 2009
                                      Posts: 2688
                                      Groups: None

                                      and it will be much more accurate than anything out there 

                                      Santosh Bhat
                                      User offline. Last seen 10 hours 4 min ago. Offline
                                      Joined: 15 Apr 2005
                                      Posts: 260

                                      Converting from MSP to P^ (or Vice Versa) is a pain, use the tool suggested by Zoltan, the time and effort it saves will pay for itself.

                                      Zoltan Palffy
                                      User offline. Last seen 22 hours 24 min ago. Offline
                                      Joined: 13 Jul 2009
                                      Posts: 2688
                                      Groups: None

                                      try this there is a free trial and you can map any field including activity codes

                                      https://xertransfer.com/

                                      Alexandre Faulx-B...
                                      User offline. Last seen 1 hour 13 min ago. Offline
                                      Joined: 20 Jan 2003
                                      Posts: 1307

                                      Hello Nathan,

                                      I have just tried another time to make sure I will not say something wrong;

                                      when you save the ms project as an xml file, the relationships are well included in the xml file, and then well imported and displayed in P6

                                      as far as activity codes are concerned, edit the import model in the P6 import-an-xml-file dialog box, go to the last tab on the right Custom fields, and set up te custom (mapped) fields as necessary