                                      Adding One Time Expense

                                      2 replies [Last post]
                                      Usman Yasin
                                      User offline. Last seen 7 weeks 7 hours ago. Offline
                                      Joined: 27 Mar 2020
                                      Posts: 4
                                      Groups: None

                                      How can i add one time expenses for a project in the total cost that will add up in the total cost but should not distribute in any activity?

                                      Replies

                                      Patrick Mullen
                                      User offline. Last seen 6 days 11 hours ago. Offline
                                      Joined: 15 May 2020
                                      Posts: 10
                                      Groups: None

                                      Hi Usman,

                                      By the sound of it, you just want one activity to equal your total cost on the project. If you don't need to utilize the histograms, then just create a user defined field and call it "Total Expense Cost", and input the value to the activity that you desire.

                                      Regards,

                                      Patrick

                                      Zoltan Palffy
                                      User offline. Last seen 21 hours 20 min ago. Offline
                                      Joined: 13 Jul 2009
                                      Posts: 2688
                                      Groups: None

                                      create a LOE activity 

                                      make the predcessors is a SS relationship with the 1st activity 

                                      make the successor a ff relationship with the last activity in the schedule 

                                      create a resource call it lumpsum

                                      assign the resource to loe activity

                                      add the cost for the project to the resource

                                      then assign a curve to the resource 

                                       